LGD: Financial Results of LITGRID AB Group for the first nine months of 2011

Spekuliantai.lt | 2011-11-30 | NASDAQ OMX biržų naujienos | perskaitė: 640
LGD: Financial Results of LITGRID AB Group for the first nine months of 2011

LITGRID AB Interim information 30.11.2011

Financial Results of LITGRID AB Group for the first nine months of 2011

Vilnius, Lithuania, 2011-11-30 13:52 CET (GLOBE NEWSWIRE) -- LITGRID AB, the
Lithuanian electricity transmission system operator, transmitted 6.84 billion
kWh of electricity via the high-voltage electricity grid for domestic needs
during the first nine months of 2011, or 1.8% more compared with the first nine
months of 2010. The amount of electricity transmitted to the distribution
network operator LESTO AB totalled 5.99 billion kWh, an increase of 0.5%
compared with the respective period last year, while the amount transmitted to
other consumers was 0.85 billion kWh, an increase of 12.1%.

The income of LITGRID group totalled LTL 313.2 million in January-September
2011. The income from electricity transmission accounted for 48% of the total
income of the group.

The EBITDA of LITGRID group for the first nine months of 2011 reached LTL 86.9
million and the EBITDA margin was 30.6%.

In January-September 2011, the net loss of LITGRID group reached LTL 12.6
million. The main cause of the loss was the fact that depreciation and
amortisation expenses in the financial statements (LTL 99.7 million during the
first nine months of 2011) are significantly higher than those calculated while
adjusting the transmission tariff (LTL 40.3 million).

In 2011, LITGRID invested LTL 136.4 million. Most investments, LTL 92.1
million, or 67% of the total invested amount, were related to the
implementation of the strategic projects NordBalt and LitPol Link.

During January-September 2011 the special plan for LitPol Link was approved, an
international public procurement of the technical project for the expansion of
the Alytus transformer substation was announced, NordBalt marine test cable is
being tested and the contractor for the Klaipėda-Telšiai power line
construction project was selected. The investments into the reconstruction and
development of the transmission grid reached LTL 44 million (32% of the total
amount).




Vilija Railaitė
Head of Communications
Phone +370 5278 2361
Mobile +370 613 19977
E-mail [email protected]


1. 2011 11 30_Atsakingu_asmenu_patvirtinimas_eng.pdf
(https://newsclient.omxgroup.com/cds/DisclosureAttachmentServlet?messageAttachmentId=370554)
2. 2011 11 30_LITGRID_FA_2011_09_30_ENG.pdf
(https://newsclient.omxgroup.com/cds/DisclosureAttachmentServlet?messageAttachmentId=370555)

Taip pat skaitykite

DPK: Decisions of the regular meeting of shareholders dated 27.05.2013

VLN: NEW MUTUAL FUND TO THE BALTIC FUND CENTER

VLN: The results of the primary placement auction of Lithuanian Government securities

VLN: VVP pirminio platinimo aukciono rezultatai

2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos

Komentarai



Ekonominis kalendorius

Prekybos statistika realiu laiku

Techninės analizės įrankis

Privatumo politika Reklama Kontaktai Paskolos RSS RSS
© 2006-2024 UAB All Media Digital