LGD: Interim Financial Results of LITGRID AB Group for the First Half of the Year 2011

Spekuliantai.lt | 2011-08-31 | NASDAQ OMX biržų naujienos | perskaitė: 1008
LGD: Interim Financial Results of LITGRID AB Group for the First Half of the Year 2011

LITGRID AB Interim information 31.08.2011

Interim Financial Results of LITGRID AB Group for the First Half of the Year
2011

Vilnius, Lithuania, 2011-08-31 15:58 CEST (GLOBE NEWSWIRE) -- LITGRID AB, the
Lithuanian transmission system operator, during the first half of year 2011
transmitted 4.62 billion kWh of electricity for domestic needs through the
high-voltage electricity grid, that is 2 per cent more than during the first
half of 2010. The volume of electricity, transmitted to the distribution
network operator LESTO AB totalled 4.08 billion kWh - 0.6 per cent more than
during the first half of 2010, to other consumers - 0.54 billion kWh, or 13.6
per cent more.

During the first half of 2011 the income of LITGRID group was LTL 209.1
million. The income from electricity transmission contributed 49 per cent of
the total income of the group's total income.

The EBITDA of LITGRID group for the first half of 2011 stood at LTL 61.2
million, while the EBITDA margin was 29.3 per cent.

In the first half of 2011 the net loss of LITGRID group was LTL 4.6 million.
The main cause for the loss of the group was the fact that depreciation and
amortization expenses in the financial statements (in the first half of 2011 -
LTL 66.4 million) are significantly higher than the expenses, calculated while
adjusting the transmission tariff (LTL 26.9 million).

During 2011 LITGRID AB invested LTL 113.1 million. The bulk part of the
investments was allocated to implementation of strategic projects - LTL 88
million or 78 per cent of total investments. The investments into
reconstruction and development of the transmission grid amounted to LTL 24
million (22 per cent of total investments).

While implementing strategic electric power projects, the publicity procedures
of the planning stage of the cross-border electricity interconnections LitPol
Link and NordBalt were completed and NordBalt marine cable tests were commenced
in the first half of 2011.

This information is not confidential.


Vilija Railaitė
Head of Communications
Phone +370 5278 2361
Mobile +370 613 19977
E-mail [email protected]


1. 2011 08 25_LITGRID_IFRS_2011-06-30_EN.pdf
(https://newsclient.omxgroup.com/cds/DisclosureAttachmentServlet?messageAttachmentId=360947)
2. 2011 08 31_LITGRID AB ENG.pdf
(https://newsclient.omxgroup.com/cds/DisclosureAttachmentServlet?messageAttachmentId=360943)
3. 2011 08 31_Atsakingu asmenu patvirtinimas.pdf
(https://newsclient.omxgroup.com/cds/DisclosureAttachmentServlet?messageAttachmentId=360926)

Taip pat skaitykite

DPK: Decisions of the regular meeting of shareholders dated 27.05.2013

VLN: NEW MUTUAL FUND TO THE BALTIC FUND CENTER

VLN: The results of the primary placement auction of Lithuanian Government securities

VLN: VVP pirminio platinimo aukciono rezultatai

2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos 2013-05-27 | NASDAQ OMX biržų naujienos

Komentarai



Ekonominis kalendorius

Prekybos statistika realiu laiku

Techninės analizės įrankis

Privatumo politika Reklama Kontaktai Paskolos RSS RSS
© 2006-2024 UAB All Media Digital